> the plan would be:
> - Mar 14 evening - the latest version bumps, time to sync the archs
>
> there are a few exceptions:
> - if firefox 2.0.0.3 will be out, that'll come with a bunch of
> security fixes, we should include it imho (it will be out on 15th
> probably)
> - gnome 2.6.18
>
> - Mar 15 evening - ful freeze, really no more version bumps, if it's a
> musthave, then _please_ ask here (on -devel) first
> - Mar 16 evening - end of syncing, we should stop uploading binary
> packages
> - Mar 18 - creating the -0.6 tree, generating the candidate final isos,
> testing
> - Mar 20 evening - uploding the final isos, waiting for the mirrors to
> be in sync
> - Mar 22 morning - release
Yep, this is OK. GNOME 2.18 is nearly done, I should have it finished by