i would propose the followings:
- nov 29 evening: latest release bumps
- nov 30 evening: upload snapshot net,cd1-2 isos to -current-iso for
testing
- dec 01 evening: update -testing
- dec 02 evening: final upload of the release isos
- dec 04 morning: release
so basically we have two days to push new features, then the usual
release dance could begin. is this ok?
thanks,
- VMiklos